Project: BuckRV-8   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Buck Wyndham   -  
Project:   Vans - RV-8   -   VIEW REPORTS
Total Hours:3914.15
Start/Last Date:Jan 08, 2002 - No Finish Date
Engine:AeroSport Power IO-375-M1S
Propeller:Whirlwind 330-3B/72H-73 3-blade CS
Panel:G3X, G5, GTN650, GTR20, GTX45R, GMA245, GMC507
 
Friendly URL: https://eaabuilderslog.org?s=BuckRV-8

Home or Last Project Picture

May 01, 2009     Aft canopy slide rail; Side rails - (2.1 hours)       Category: Fuselage
Today I backdrilled the last slide rail support mounting hole, up through the fuselage and through the aft canopy slide rail support. Next, I assembled the slide rail and the support piece by setting all the double-flush rivets. (I discovered that, although Vans calls for AN426AD3-6s here, 3-6s are too short. 3-7s work much better.) With the exception of countersinking the screw holes and chrome-plating, the aft slide rail is complete.

Next, I cut the canopy side rails to length per the plans. With help from my friend Jim, I positioned the rails on the fuselage and taped them in place to check the fit of the canopy frame. I assembled the canopy rollers and temporarily installed them in the frame. Then we put the canopy frame on the rails and slid it back and forth to check its operation. After tweaking the rail position, the canopy was still a little sticky near the middle of its travel, but I think this will get better with time and proper lubrication. I'll play with it a bit more next time.


 


NOTE: This information is strictly used for the EAA Builders Log project within the EAA organization.     -     Policy     -     © Copyright 2024 Brevard Web Pro, Inc.